The Billion-Dollar Website

The Government Accountability Office has investigated the cost blowouts associated with how the Centers for Medicare & Medicaid Services (CMS) handled the Healthcare.gov project. It has released a 60-page report entitled Healthcare.gov: Ineffective Planning and Oversight Practices Underscore the Need for Improved Contract Management, with a 5 page summary. The key takeaway messages are:
  • CMS undertook the development of Healthcare.gov and its related systems without effective planning or oversight practices...
  • [The task] was a complex effort with compressed time frames. To be expedient, CMS issued task orders ... when key technical requirements were unknown...
  • CMS identified major performance issues ... but took only limited steps to hold the contractor accountable.
  • CMS awarded a new contract to another firm [and the new contract's cost has doubled] due to changes such as new requirements and other enhancements...